Project Photos
Phase Two: Student Recreation Center Construction
Construction of the Student Recreation Center will take place from July 2006 and is anticipated to be completed by January 2008.
Project Budget - $41,870,000
Architects – Langdon Wilson Architects
Contractor – C. W. Driver
Project Manager – Will Nighswonger
Photos
Student Recreation Center Debut April 9, 2008 Photos by: Kelly Lacefield
Rock Wall January 4, 2008
Construction November 30, 2007
Construction September 29, 2007
Construction April 2007
Trusses Lifted March 2007
February 2007
January 26, 2007
Wall Raising January 2007
January 10, 2007
December 2006
November 2006
October 2006
July 2006
Phase One: Upgrading Building Systems
The Titan Student Union's single 300 ton chiller will be replaced with two more energy efficient 350 ton chillers that will serve as primary cooling systems for both the TSU and the future Student Recreation Center facility. The project also includes the installation of a series of boilers designed to support the space heating requirements of both the TSU and the future recreation center. Both the chiller and boiler equipment will be physically located in the area immediately south of the student union.
The final aspect of this project phase is the installation of buried hydronic piping which will run from the south area of the student union to the recreation center site. This piping is required to deliver heating and cooling capacity from these new systems to the future recreation center.
Photos - Jan & March 2006
|