Expected Project Timeline
Project Background
October 1999
ASI President facilitated a one-day student empowerment session and identified student’s recreational needs
December 1999
TSU Board approved a motion to hire Brailsford & Dunlavey to conduct a student recreation feasibility study.
March 2000
Brailsford & Dunlavey submitted feasibility study. Results indicated a strong study interest in building a student recreation center on the CSUF campus.
March 2000
TSU Board, ASI Board, and Student Fee Advisory Committee approved a student fee referendum to support the building of a student recreation center.
April 2000
Informational campaign was conducted.
May 2000
Referendum passed 1,103 to 486 votes (69% = yes, 31% = no).
May 2000
Recommendation to President’s Advisory Board was approved.
April 2001 – December 2001
Planning Committee Activities
- Developed preliminary project timeline
- Conducted campus recreation center site visits
- University of California, Irvine
- University of California, San Diego
- University of California, Riverside
- San Diego State University
- University of Texas at Austin (2 facilities)
- Texas A & M University
- Baylor University
- Debriefed each visit, collected notes, and synthesized committee member input
- Conducted group exercise to develop guiding design principles
- Conducted group exercise to prioritize spaces included in program plan
- Developed program plan
- Program plan endorsed by TSU Board, ASI Board, President’s Advisory Board
April 2002 – July 2002
Architect Selection Committee
- Researched and interviewed six architectural firms
- Recommended Langdon Wilson to be awarded 90-day Pre-design phase
- TSU Board and ASI Board approved recommendation
October 2002 – February 26, 2004
Building Committee
- Tested program planning assumption
- Verified program, site and square footage
- Verified budget projections
- Developed and tested conceptual designs
Spring 2004
Schematic Design Approval
- Received approval by ASI Board of Directors and TSU Governing Board
January 2005
Construction Management Firm Selection
- Researched and interviewed management firms
- Recommended CW Driver as the construction management firm
- TSU Governing Board and ASI Board of Directors approved recommendation
Spring 2005
President's Advisory Board
- Presented the Student Recreation Center Project to the President's Advisory Board
- Received approval to move forward with project
|