PROJECT TIMELINE

PROJECT TIMELINE


Demolition of Expansion Site: August – October 2015

Excavation for Expansion Lower Level: November 2015

Foundation and Basement Walls Installed: November 2015 – December 2015

Relocation of TSU Information and Services Desk: January 2016

Structural Steel Framing: December 2015 – February 2016

Floors and Roofing: January 2016 - April 2016

Windows and External Walls: April 2016 – July 2016

Exterior Upgrades: February 2016 – August 2016

Interior Walls and Floors: February 2016 – Spring 2017

Exterior Landscaping: Spring 2017